My new online project...

Sunday, 17 June 2018

Karczunkowska viaduct - further delays likely

It's almost two months to the day ul. Karczunkowska was closed so that a viaduct could be built, taking it over the newly-modernised Warsaw-Radom railway line. Things have settled down a bit; the temporary level crossing, opened last spring, is doing its job. But while the viaduct itself is growing, there seem to be problems with the ramps at either side.

Below: the approach road is taking shape at the western end. The tight bend here is good - it will slow down traffic.


UPDATE: Friday, 22 June, and I can see more clearly what's going on here. This is actually the access road to ul. Kurantów and ul. Gogolińska, this suggests that there won't be another span of viaduct crossing Gogolińska at its junction with Karczunkowska.


Contractor PRKiI has announced that from 22:00 this Thursday, 21 June, until 20:00 on 21 August, Karczunkowska will be closed on the short stretch between Gogolińska and Kurantów for the construction of retention walls and mains sewers. They did this earlier this spring (from 27 April to 7 May). re-opening bang on time. Now, it's not ten days, it's 61 days. Lots of opportunities for things to go wrong... If you click to enlarge the photo below, you'll see ul. Gogolińska running off to the right at 90 degrees to Karczunkowska. To keep this road open, the viaduct will need a further set of pillars between the wall you see and the near side of Gogolińska, plus access to Kurantów. This is almost as big a job as throwing the bridge over the tracks.

UPDATE: Friday 22 June - the road will be closed at 22:00 hours tonight, 26 hours after the original date. How long will it stay closed?


In the meanwhile, as happened last time this stretch of road was closed, there are the eternally optimistic drivers who believe that the five no entry/road closed signs do not actually apply to them. They will carry on heading east along Karczunkowska, then seeing barriers and heavy construction equipment, they'll turn into Kurantów. Those equipped with Google Maps (below) may see that at the end of Kurantów, they can swing right and soon be on Gogolińska, and hop-skip-jump, they're across the tracks. Let me show them (in good time) that Google Maps is WRONG. Click to enlarge. I've marked the closed section in pink, and the highlight in pale green the bit of ul. Kurantów that is not actually a road, but a very narrow footpath running through an overgrown field.


Below: local residents, annoyed by these optimist drivers, have put up a sign. 'STOP! TURN AROUND THE ROAD ENDS IN 80 METRES'


Below: indeed it does. There is a footpath, between the wheelie bins and the post; it is wide enough for pedestrian, but waist-high in grass. You could do this on a mountain bike or enduro motorbike, but you'll spend half an hour extracting vegetation from the chain and spokes. In other words - don't bother. The alternative, however, is an 8km detour via Baletowa.


Meanwhile, across the tracks, this is how things are looking. But word is (and I've heard this from two local residents) that the ramp that will carry the roadway up to the viaduct has been badly planned, and will end on the wrong side of the turn-off for Biedronka (on one side of Karczunkowska) and ul. Nawłocka (on the other). The answer is to make it steeper, with the possibility of a roundabout at this junction to slow traffic down. One way or the other, the re-planning of the gradient of the on-ramp means further delays.


Below: view from the 'up' platform - the first set of steps are appearing. These will allow people to walk up to the viaduct from ul. Gogolińska.


Below: for the convenience of passengers from across the track travelling into town, now that the scaffolding has been removed from the viaduct, a new footpath has been laid alongside the coal train line, saving a detour of 120 metres.



All in all, progress is far slower than planned. Here's a quote from Piaseczno News from just three weeks ago:

– Jeśli chodzi o wiadukt, to ma być on gotowy na przełomie III i IV kwartału tego roku. Utrzymane jest tam dobre tempo prac – podkreśla Karol Jakubowski z biura prasowego PKP PLK.. Widać już konstrukcję budowli. W tej chwili wykonywane są podtrzymujące wiadukt filary. Cały czas trwają także prace przy budowie zjazdów.

"As far as the viaduct is concerned, it is to be ready at the turn of the third and fourth quarter of this year. A good pace of work is maintained there," emphasises Karol Jakubowski from the press office of PKP PLK... "The construction of the building is already visible. At the moment, the pillars supporting the flyover are being built. The construction of the congresses is also in progress all the time." [Translated with www.DeepL.com/Translator]

End of September? No. Way.

This time six years ago:
Russia's going home

This time 11 years ago:
Sun and zenith rising




2 comments:

  1. So near and yet so far...

    ReplyDelete
  2. @ Ian -my main concern is the eastern ramp. If my sources are correct, this will take a long time to sort out, as it will be back to the drawing board.

    ReplyDelete